On Monday 23 November at 16:00 (UTC+1), the Migliarini project will open for investment. This new debt investment opportunity will partially finance the acquisition and completion of a residential development comprising 18 new-build homes in Rome.
Construction is already under way, with the building’s structure completed and overall progress at approximately 30%. Urbanitae investors will provide a loan of €1 million, with an 18-month term and a fixed interest rate of 10% simple annual interest.
- Investment opening: Monday 23 November at 16:00 (UTC+1)
- Amount: €1,000,000
- Term: 18 months + possible six-month extension
- Interest: 10% simple annual interest
- Total return over the standard term: 15%
- Minimum return: nine months’ interest, equivalent to 7.5%
18 new-build homes in Rome
The development is located at Via Michele Migliarini 58, in Gregna Sant’Andrea, south-east of Rome and close to the Capannelle area.
The building will comprise 18 one- and two-bedroom homes, all with independent entrances and outdoor space: private gardens on the ground floor and balconies on the upper floors.
The development will also include 18 parking spaces and a rooftop terrace measuring over 520 m².
The homes will achieve an A4 energy rating, the highest under the Italian system, and will feature photovoltaic installations and fully electric systems for heating, cooling and cooking.
Construction is already under way
One of Migliarini’s distinguishing features is that the project is not starting from an undeveloped plot.
The building’s reinforced concrete structure was completed in June 2026, and much of the external enclosure work has already been carried out. Overall construction progress currently stands at around 30%.
The project has obtained its permesso di costruire (building permit) and the corresponding administrative amendment authorising an increase from 16 to 18 homes.
The remaining works will be carried out under a fixed-price turnkey contract, with an expected duration of approximately 12 months. Construction is scheduled for completion in October 2027.
What will the loan be used for?
The property will be acquired for €1.9 million. The developer has already paid a €500,000 deposit, and the final purchase deed will be executed at the same time as Urbanitae’s loan agreement and the registration of the mortgage.
The €1 million provided by Urbanitae investors will finance part of the outstanding acquisition price and the initial project costs.
The total senior financing may reach €2.8 million. In addition to Urbanitae’s loan, other investors will contribute up to €1.8 million, primarily to finance construction.
This additional financing cannot begin to be drawn down until six months have elapsed. Drawdowns will also be subject to certain conditions, including achieving a 25% pre-sales level and having construction progress certified by an independent Project Monitor.
The developer contributes 35% of project costs
The developer has committed approximately €1.52 million in equity, equivalent to 35% of the project’s total estimated costs.
Of this amount, approximately €1.18 million will be contributed at closing, including the €500,000 already paid as a deposit.
The developer will also be responsible for potential cost overruns through a completion and cost overrun guarantee, meaning that any deviation from the agreed budget must be covered with additional funds.
10% annual interest over 18 months
The main loan terms are:
- Amount: €1,000,000.
- Interest: 10% simple annual interest.
- Standard term: 18 months.
- Total return: 15%.
- Possible extension: an additional six months.
- Minimum return: nine months’ interest, equivalent to 7.5%.
- Principal and interest: payable at maturity.
Early repayment may take place at any time, provided that the minimum return is respected.
If the extension is used, a 1% fee will apply and certain conditions must be met, including construction having reached at least 80% completion.
An extensive security package
The loan is secured by a first-ranking mortgage over the property, which will be registered at the same time as the purchase deed.
Additional security includes:
- A first-ranking pledge over the borrower’s bank accounts.
- An on-demand corporate guarantee from a company belonging to the developer’s group, capped at 150% of the principal.
- Assignment by way of security of the net proceeds from any future sale of another property owned by the group in Rome.
- An undertaking not to encumber that property with new debt.
- A completion and cost overrun guarantee provided by the developer.
- An irrevocable mandate to sell, which may be activated during the final six months of the loan and is subject to a minimum sale price of 75% of the latest available valuation.
An LTGDV of approximately 51%
The total financing represents an LTGDV of approximately 51% of the development’s projected sales value.
LTGDV compares the outstanding debt with the estimated value of a project once completed and sold. In this case, it means that the total loan represents approximately half of the expected revenue from selling the homes and parking spaces.
Furthermore, debt levels are restricted during the initial stages: drawdowns that would push the LTC above 40% are conditional on achieving 25% pre-sales and obtaining certification of construction progress.
This approach ensures that increases in financing are linked to actual construction and sales progress.
How will the loan be repaid?
The planned exit is straightforward: the sale of the homes and parking spaces.
Marketing and sales will begin while construction is under way, and the proceeds from these sales will be used to repay the financing.
An independent commercial due diligence assessment estimates the completed development’s value at approximately €5.18 million, in line with the business plan assumptions.
The projected average price of approximately €3,487/m² falls within the range observed for comparable new-build developments analysed in the area.
Why invest in Migliarini?
We believe that Migliarini brings together several important features for a residential debt investment: construction already under way, permits in place, a substantial equity contribution from the developer and an extensive security package.
Key highlights include:
- 10% simple annual interest.
- 15% total return over the standard 18-month term.
- Minimum return equivalent to nine months’ interest, or 7.5%.
- First-ranking mortgage over the property.
- On-demand corporate guarantee covering up to 150% of the principal.
- Developer with approximately €1.52 million in committed equity.
- Building structure already completed, with overall construction progress close to 30%.
- Remaining works to be carried out under a fixed-price turnkey contract.
- Additional drawdowns conditional on construction progress and achieving 25% pre-sales.
- LTGDV of around 51%.
- Exit through the sale of 18 new-build homes in Rome.
Estimated timeline
The standard investment term is 18 months, with a possible six-month extension.
The main expected milestones are:
- November 2026: loan disbursement, acquisition of the property and continuation of construction.
- October 2027: expected completion of construction.
- May 2028: expected repayment of Urbanitae’s loan through the sale of the homes and parking spaces.
As with any property development, these dates may change depending on construction and sales progress.
Do you have any questions about the project?
Migliarini will open for investment on Monday 23 November at 16:00 (UTC+1).
If you have any questions about the project, you can email us at contacto@urbanitae.com or call us on (+34) 911 23 25 22.